一, construction preparation
(1) Technical preparation
1) Before masonry, be familiar with the drawings carefully and review the construction drawings.
2) Prepare the floor construction plan. 3) Before floor construction, construction technology disclosure should be organized.
3) Formulate the quality objectives of the sub-project, check and acceptance system and other measures to ensure the quality of the project.
(2) Material preparation:
Antistatic floor, movable support, copper strip, kicker line, aluminum Angle strip, sealant.
(3) Preparation of construction facilities:
Cutting machine, screwdriver, level, steel measuring tape, measuring tape, level,.
(4) Preparation of working conditions:
1) Clean up the garbage, stains and ground ash at the base level.
2), the wire tube should do a good job of trying on the work, and the wire tube is processed before construction.
3), the indoor wall play the building 1m horizontal line, and do a good job of review work. After review, go through the relevant procedures.
二, green construction
1. Regular maintenance and maintenance of the construction equipment to ensure the normal operation of the equipment.
2, temporary facilities to use electrical equipment marked with "CCC mark qualified products.
3. Materials purchased during construction should meet the requirements of green materials in design. The indicators of the material should meet the requirements of the current national green building materials standard.
4. Reduce the material loss rate in the process of material transportation and strengthen the material utilization rate in the construction process.
5, compare the actual construction material consumption and calculate the material consumption, improve the material saving rate.
6. Make full use of the site and surrounding existing or proposed roads during construction.
7. The construction waste that can be recycled shall be directly reapplied in the construction process, or processed and reused through the recycling plant.
三,safety and civilized construction
1. Security management
(1) The safety helmet must be worn when entering the construction site.
(2) During operation, construction personnel must wear flat rubber shoes without nails, so as not to scratch the board surface.
(3) There should be enough lighting for the construction at night, and temporary lighting lines should not be moved casually.
(4) The cutting machine should be operated with good insulation gloves, while ensuring the safety of electricity.
(5) Use and management of standard on-site temporary power, strictly abide by the three-level power distribution and two-level protection, and often check the safety and reliability of power distribution equipment.
2. Civilized construction
[1] All kinds of materials shall be stacked neatly, beautifully and reasonably on site.
[2] After the completion of construction every day, the working surface should be cleaned and the spilled waste should be cleaned up.
[3] It is required that construction personnel at all operation surfaces should carry out construction in a civilized manner, transport construction materials and construction wastes to designated garbage dumps, and not throw them away randomly. It is required to strengthen the management of construction sites and garbage stations, and do a good job in sorting and recycling residual materials